MAY 2021

Sunday, May 23 – Saturday, May 29, 2021  

Scheduled activity is weather permitting 

ā€‹

Sunday, May 23

  • No construction activity scheduled.

ā€‹

Monday, May 24 – Thursday, May 27

  • Excavation, backfilling and base repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of PCC foundation for traffic signal/pendant post streetlights at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of PVC conduit at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of electrical manholes at Columbia Road/Harvard Street/Mt. Pleasant Street NW.   

  • Verification of existing conditions of electrical work from Park Road to Lamont Street NW.  

ā€‹

Friday, May 27 – Saturday, May 29  

  • No construction activity scheduled due to the Memorial Day Holiday. 

Sunday, May 16 – Saturday, May 22, 2021  

Scheduled activity is weather permitting 

ā€‹

Sunday, May 16

  • No construction activity scheduled.

ā€‹

Monday, May 17 – Friday, May 21

  • Installation of wheelchair ramps at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Excavation, backfilling and repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of PCC foundation for traffic signal/pendant post streetlights at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Removal of steel transformer base and abandoned traffic signal pole foundation at Columbia Road/Harvard Street/Mt. Pleasant Street NW. 

  • Installation of PVC conduit at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of electrical manholes at Columbia Road/Harvard Street/Mt. Pleasant Street NW.   

  • Verification of existing conditions of electrical work from Park Road to Lamont Street NW.

ā€‹

Saturday, May 22 

  • No construction activity scheduled.

Sunday, May 9 – Saturday, May 15, 2021  

Scheduled activity is weather permitting 

ā€‹

Sunday, May 9

  • No construction activity scheduled.

ā€‹

Monday, May 10 – Friday, May 14

  • Installation of wheelchair ramps at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Excavation, backfilling and repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of brick gutter at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of PCC foundation for traffic signal/pendant post streetlights at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Removal of steel transformer base at Columbia Road/Harvard Street/Mt. Pleasant Street NW. 

  • Installation of PVC conduit at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of electrical manholes at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Verification of existing conditions of electrical work from Park Road to Lamont Street NW. 

ā€‹

Saturday, May 15 

  • No construction activity scheduled.

Sunday, May 2 – Saturday, May 8, 2021  

Scheduled activity is weather permitting 

ā€‹

Sunday, May 2

  • No construction activity scheduled.

ā€‹

Monday, May 3 – Friday, May 7

  • Installation of wheelchair ramps at Columbia Road/Harvard Street/Mt. Pleasant Street NW. 

  • Excavation, backfilling and repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW. 

  • Installation of PCC foundation for traffic signal/pendant post streetlights at Columbia Road/Harvard Street/Mt. Pleasant Street NW. 

  • Installation of PVC conduit at Columbia Road/Harvard Street/Mt. Pleasant Street NW. 

  • Installation of electrical manholes at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Please note: Parking will be restricted on the northbound side of 16th Street NW at Columbia Road NW from 7:00 a.m. to 5:00 p.m., Monday – Friday.

ā€‹

Saturday, May 8 

  • No construction activity scheduled.