JUNE 2021

Sunday, June 27 – Saturday, July 3, 2021  

Scheduled activity is weather permitting 

Sunday, June 27

  • No construction activity scheduled.

Monday, June 28 – Thursday, July 1 

  • Verification of existing conditions of electrical work at Pine Street NW. 

  • Excavation, backfilling, base repairs and sidewalk repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Removal of island/site work at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of PCC foundation at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of granite curb at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of underdrain pipe at Columbia Road/Harvard Street/Mt. Pleasant Street NW. 

Friday, July 2 – Saturday, July 3

  • No construction activity scheduled due to the Independence Day Holiday weekend. 

Sunday, June 20 – Saturday, June 26, 2021  

Scheduled activity is weather permitting 

Sunday, June 20

  • No construction activity scheduled.

Monday, June 21 – Friday, June 25 

  • Verification of existing conditions of electrical work from Park Road to Lamont Street NW.  

  • Installation of poles at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Excavation, backfilling, base repairs and sidewalk repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Removal of island/site work at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of granite curb at Columbia Road/Harvard Street/Mt. Pleasant Street NW.

Saturday, June 26

  • No construction activity scheduled.

Sunday, June 13 – Saturday, June 19, 2021  

Scheduled activity is weather permitting 

Sunday, June 13

  • No construction activity scheduled.

Monday, June 14 – Friday, June 18 

  • Installation of blackout foundations from Park Road to Lamont Street NW. 

  • Verification of existing conditions of electrical work from Park Road to Lamont Street NW.  

  • Installation of poles at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of wheelchair ramps at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Excavation, backfilling, base repairs and sidewalk repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of brick gutter and basin connect/PCC pipe at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of PCC foundation at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Removal of abandoned traffic signal/pole foundation at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Worked on erosion control at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of grate inlets at Columbia Road/Harvard Street/Mt. Pleasant Street NW

Saturday, June 19

  • No construction activity scheduled.

Sunday, June 6 – Saturday, June 12, 2021  

Scheduled activity is weather permitting 

Sunday, June 6

  • No construction activity scheduled.

Monday, June 7 – Friday, June 11 

  • Excavation, backfilling and base repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of underdrain pipe at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of granite curbs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Verification of existing conditions of electrical work from Park Road to Lamont Street NW. 

Saturday, June 12

  • No construction activity scheduled.

Sunday, May 30 – Saturday, June 5, 2021  

Scheduled activity is weather permitting 

Sunday, May 30 – Monday, May 31 

  • No construction activity scheduled due to the Memorial Day Holiday.

Tuesday, June 1 – Friday, June 4 

  • Excavation, backfilling and base repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of wheelchair ramps at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of PCC foundation for traffic signal/pendant post streetlights at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of underdrain pipe at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Work on erosion control at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of grate inlet at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of PVC conduit at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Verification of existing conditions of electrical work from Park Road to Lamont Street NW. 

Saturday, June 5

  • No construction activity scheduled.