FEBRUARY 2022
Sunday, February 20 – Saturday, February 26, 2022
Scheduled activity is weather permitting
Sunday, February 20
-
No construction activity scheduled.
Monday, February 21
-
No construction activity scheduled due to the President’s Day Holiday.
Tuesday, February 22 – Friday, February 25
-
Removal of foundations and structural cleanouts from U Street NW to V Street NW.
-
Installation of signs from U Street NW to V Street NW.
-
To view the traffic advisory for this activity, please click here.
Saturday, February 26
-
No construction activity scheduled.
Sunday, February 13 – Saturday, February 19, 2022
Scheduled activity is weather permitting
Sunday, February 13
-
No construction activity scheduled.
Monday, February 14 – Friday, February 18
-
Installation of signs from U Street NW to V Street NW.
Saturday, February 19
-
No construction activity scheduled.
Sunday, February 6 – Saturday, February 12, 2022
Scheduled activity is weather permitting
Sunday, February 6
-
No construction activity scheduled.
​
Monday, February 7 – Friday, February 11
-
Excavation and extension of Bump Out from U Street NW to V Street NW.
Saturday, February 12
-
No construction activity scheduled.
Sunday, January 30 – Saturday, February 5, 2022
Scheduled activity is weather permitting
Sunday, January 30
-
No construction activity scheduled.
​
Monday, January 31 – Friday, February 4
-
Excavation and extension of Bump Out from U Street NW to V Street NW.
-
Installation of catch basin from U Street NW to V Street NW.
-
Installation and connection of pipes from U Street NW to V Street NW.
-
Installation of granite curbs from U Street NW to V Street NW.
-
Special Notice: All signals at Columbia Road/Harvard Street/Mt. Pleasant Street NW are anticipated to be turned on by February 4, 2022. In the meantime, please pay attention to traffic signs as you are traveling in this area.
-
To view the traffic advisory for this activity, please click here.
Saturday, February 5
-
No construction activity scheduled.