MARCH 2022
Sunday, March 27 – Saturday, April 2, 2022
Scheduled activity is weather permitting
​
Sunday, March 27
-
No construction activity scheduled.
Monday, March 28 – Friday, April 1
-
Red paint bus lane striping from Arkansas Avenue NW to Newton Street NW.
-
Installation of center lane signs.
-
Milling and paving from Crescent Place NW to Euclid Street NW.
-
To view the traffic advisory in place for these activities, please click here.
-
To view the anticipated schedule for red paint striping, please click here.
-
To view the anticipated schedule for milling and paving, please click here.
Saturday, April 2
-
No construction activity scheduled.
Sunday, March 13 – Saturday, March 19, 2022
Scheduled activity is weather permitting
Sunday, March 13
-
No construction activity scheduled.
Monday, March 14 – Friday, March 18
-
Installation of signage, cabinets and delineators from Arkansas Avenue NW to Irving Street NW.
-
To view the traffic advisory for this activity, please click here.
Saturday, March 19
-
No construction activity scheduled.
Sunday, March 6 – Saturday, March 12, 2022
Scheduled activity is weather permitting
Sunday, March 6
-
No construction activity scheduled.
Monday, March 7 – Friday, March 11
-
Installation of signs and cabinets from U Street NW to V Street NW.
Saturday, March 12
-
No construction activity scheduled.
Sunday, February 27 – Saturday, March 5, 2022
Scheduled activity is weather permitting
Sunday, February 27
-
No construction activity scheduled.
Monday, February 28 – Friday, March 4
-
Installation of signs from U Street NW to V Street NW.
-
To view the traffic advisory for this activity, please click here.
Saturday, March 5
-
No construction activity scheduled.
​
​
​
​
​