AUGUST 2021
Sunday, August 29 – Saturday, September 4, 2021
Scheduled activity is weather permitting
Sunday, August 29
-
No construction activity scheduled.
Monday, August 30 – Friday, September 3
-
Milling, paving, and striping operations from Irving Street NW to Euclid Street NW (milling and some striping will take place during the daytime hours of 9:30am – 3:30pm; paving and some striping will take place during the overnight hours of 8:00pm – 5:00am). Click here for more information regarding milling, paving and striping or to view a video of the process, Click here. To view the overall schedule,
please Click here.
Saturday, September 4
-
No construction activity scheduled.
Sunday, August 22 – Saturday, August 28, 2021
Scheduled activity is weather permitting
Sunday, August 22
-
No construction activity scheduled.
Monday, August 23 – Friday, August 27
-
Construction management for additional conduit and electric manholes to bypass Pepco vaults at Pine Street NW.
Saturday, August 28
-
No construction activity scheduled.
Sunday, August 15 – Saturday, August 21, 2021
Scheduled activity is weather permitting
Sunday, August 15
-
No construction activity scheduled.
Monday, August 16 – Friday, August 20
-
Construction management for additional conduit and electric manholes to bypass Pepco vaults at Pine Street NW.
Saturday, August 21
-
No construction activity scheduled.
Sunday, August 8 – Saturday, August 14, 2021
Scheduled activity is weather permitting
Sunday, August 8
-
No construction activity scheduled.
Monday, August 9 – Friday, August 13
-
Milling, paving, and striping operations from Pine Street NW to Irving Street NW (milling and paving will take place during the daytime hours of 9:30am – 3:30pm; striping will take place during the overnight hours of 8:00pm – 5:00am). Click here for more information regarding milling, paving and striping or to view a video of the process, Click here. To view the overall schedule, please Click here.
-
Striping from Spring Place NW to Park Road NW (during the overnight hours of 8:00pm – 5:00am).
-
Construction of conduit and electric manholes to bypass Pepco vaults at Pine Street NW.
-
Please note that there will be a bus detour in place on Wednesday, August 11th from 8:00am - 4:00pm and Thursday, August 12th from 8:00am - 4:00pm for the H2, H4 and H8. Please click here for more information.
Saturday, August 14
-
No construction activity scheduled.
Sunday, August 1 – Saturday, August 7, 2021
Scheduled activity is weather permitting
Sunday, August 1
-
No construction activity scheduled.
Monday, August 2 – Friday, August 6
-
Raising manholes at Pine Street NW.
-
Installation of light poles and lights at Pine Street NW.
Saturday, August 7
-
No construction activity scheduled.