FEBRUARY 2021
Sunday, February 21 – Saturday, February 27, 2021
Scheduled activity is weather permitting
ā
Sunday, February 21
-
No construction activity scheduled.
Monday, February 22
-
No construction activity due to weather.
Tuesday, February 23 – Friday, February 26
-
Installation of PVC on the southeast side of Arkansas Avenue NW.
-
Installation of cabinet and 2 light pole bases on the southeast side of Arkansas Avenue NW.
-
Installation of PVC at Spring Road NW on the northeast side.
-
Installation of duct bank across 16th Street NW at Spring Road NW.
-
Installation of light pole foundations at Spring Road NW.
ā
Saturday, February 27
-
No construction activity scheduled.
Sunday, February 14 – Saturday, February 20, 2021
Scheduled activity is weather permitting
ā
Sunday, February 14
-
No construction activity scheduled.
ā
Monday, February 15
-
No construction activity scheduled due to the President’s Day holiday.
Tuesday, February 16 – Friday, February 19
-
Installation of PVC on the southeast side of Arkansas Avenue NW.
-
Installation of cabinet and 2 light pole bases on the southeast side of Arkansas Avenue NW.
-
Installation of duct bank across 16th Street NW at Arkansas Avenue NW.
-
Installation of light pole foundations at Arkansas Avenue NW.
-
Pedestrians channelizers installed with pedestrian detours in place at Columbia Road/Harvard Street NW.
-
Traffic barriers in place to begin excavation of roadway medians Columbia Road/Harvard Street NW.
ā
Saturday, February 20
-
No construction activity scheduled.
Sunday, February 7 – Saturday, February 13, 2021
Scheduled activity is weather permitting
ā
Sunday, February 7
-
No construction activity scheduled.
ā
Monday, February 8
-
No construction activity due to weather.
ā
Tuesday, February 9 – Friday, February 12
-
Verification of duct rod between Shepherd Street to Spring Place NW (from manhole to manhole).
-
Verification of existing conduit routes for blank sign installation between Newton Street and Spring Place NW (manhole to manhole).
ā
Saturday, February 13
-
No construction activity scheduled.
Thursday, February 4 – Saturday, February 6, 2021
Scheduled activity is weather permitting
ā
Thursday, February 4 and Friday, February 5
-
Installation of Federal Aid sign at Arkansas Avenue NW (southbound side).
-
Installation of Federal Aid sign at K Street NW (northbound side).
-
Installation of signage (Maintenance of Traffic, Road Work Ahead and End Road Work) at Mt. Pleasant Street, Columbia Road, Florida Avenue, V Street, New Hampshire Avenue, and U Street.
-
Installation of tree box protection at the 3700 block of 16th Street NW.
-
Completed test pit at the corner of 16th Street and Arkansas Avenue NW to identify conflicting utility.
ā
Saturday, February 6
-
No construction activity scheduled.