top of page

JULY 2021

Sunday, July 25 – Saturday, July 31, 2021 

Scheduled activity is weather permitting 

Sunday, July 25 

  • No construction activity scheduled. 

 

Monday, July 26 – Friday, July 30 

  • Bus pad extensions at Church Street, M Street, and K Street NW (beginning on Friday, July 30th). 

  • Milling, paving, and striping operations from Spring Place NW to Park Road NW (milling and paving will take place during the daytime hours of 9:30am – 3:30pm; striping will take place during the overnight hours of 8:00pm – 5:00am). Click here for more information regarding milling, paving and striping or to view a video of the process, Click here. To view the overall schedule, please Click here.

  • Installation of light poles and lights at Pine Street NW.  

 

Saturday, July 31 

  • Bus pad extensions at Church Street, M Street, and K Street NW (curing only). 

Sunday, July 4 – Saturday, July 10, 2021  

Scheduled activity is weather permitting 

Sunday, July 4 - Monday, July 5

  • No construction activity scheduled due to the Independence Day Holiday. 

Tuesday, July 6 – Friday, July 9  

  • Bus pad extensions at Irving Street, Fuller Street, S Street, and R Street NW (beginning on Friday, July 9) 

  • Verification of existing conditions of electrical work at Pine Street NW. 

  • Installation of light poles and lights at Pine Street NW. 

  • Excavation, backfilling, base repairs and sidewalk repairs at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Removal of island/site work at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of granite curb at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

  • Installation of underdrain pipe at Columbia Road/Harvard Street/Mt. Pleasant Street NW.  

Saturday, July 10

  • Signal and streetlight work (7:00 a.m. to 3:00 p.m.) at Columbia Road/Harvard Street/Mt. Pleasant Street NW 

bottom of page