Sunday, February 21 – Saturday, February 27, 2021
Scheduled activity is weather permitting
Sunday, February 21
- No construction activity scheduled.
Monday, February 22
- No construction activity due to weather.
Tuesday, February 23 – Friday, February 26
- Installation of PVC on the southeast side of Arkansas Avenue NW.
- Installation of cabinet and 2 light pole bases on the southeast side of Arkansas Avenue NW.
- Installation of PVC at Spring Road NW on the northeast side.
- Installation of duct bank across 16th Street NW at Spring Road NW.
- Installation of light pole foundations at Spring Road NW.
Saturday, February 27
- No construction activity scheduled.
__
Sunday, February 14 – Saturday, February 20, 2021
Scheduled activity is weather permitting
Sunday, February 14
- No construction activity scheduled.
Monday, February 15
- No construction activity scheduled due to the President’s Day holiday.
Tuesday, February 16 – Friday, February 19
- Installation of PVC on the southeast side of Arkansas Avenue NW.
- Installation of cabinet and 2 light pole bases on the southeast side of Arkansas Avenue NW.
- Installation of duct bank across 16th Street NW at Arkansas Avenue NW.
- Installation of light pole foundations at Arkansas Avenue NW.
- Pedestrians channelizers installed with pedestrian detours in place at Columbia Road/Harvard Street NW.
- Traffic barriers in place to begin excavation of roadway medians Columbia Road/Harvard Street NW.
Saturday, February 20
- No construction activity scheduled.
__
Sunday, February 7 – Saturday, February 13, 2021
Scheduled activity is weather permitting
Sunday, February 7
- No construction activity scheduled.
Monday, February 8
- No construction activity due to weather.
Tuesday, February 9 – Friday, February 12
- Verification of duct rod between Shepherd Street to Spring Place NW (from manhole to manhole).
- Verification of existing conduit routes for blank sign installation between Newton Street and Spring Place NW (manhole to manhole).
Saturday, February 13
- No construction activity scheduled.
__
Thursday, February 4 – Saturday, February 6, 2021
Scheduled activity is weather permitting
Thursday, February 4 and Friday, February 5
- Installation of Federal Aid sign at Arkansas Avenue NW (southbound side).
- Installation of Federal Aid sign at K Street NW (northbound side).
- Installation of signage (Maintenance of Traffic, Road Work Ahead and End Road Work) at Mt. Pleasant Street, Columbia Road, Florida Avenue, V Street, New Hampshire Avenue, and U Street.
- Installation of tree box protection at the 3700 block of 16th Street NW.
- Completed test pit at the corner of 16th Street and Arkansas Avenue NW to identify conflicting utility.
Saturday, February 6
- No construction activity scheduled.